TPK Ext (SR821) Thru Lane Implementation (MP40.2-47)
Project Summary
TPK Ext (SR821) Thru Lane Implementation (MP40.2-47)
Scope of Work
- Roadway Improvements
TPK EXT (SR821) THRU LANE IMPLEMENTATION (MP 40.2-47) - MISC ELLANEOUS CONSTRUCTION
Categories derived from the FDOT Work Program work-mix code for this project.
Contracts & Awards
- Prime contractor
- Ohla USA IncFDOT
- Contract
- E8W59FDOT
- Construction cost (this project)
- $712.1KDerived
- FDOT project manager
- Pacifico CastilloFDOT
CEI, subconsultants, project team contacts and award history are part of Pro.
Project Location
Approximate route from FDOT construction data.
Related Projects
Same Work Program item
Same roadway
- Heft Widening NW106TH To I75-DIVERGING Diamond Interchange NW 170Th StMiami-Dade County · 2020 – 2026Roadway 87471000 · MP 33.3–39.4$9.9M
- NB SR821 To NW107THAVE Buttonhook & NW107THAVE To NB SR821 FlyoverMiami-Dade County · 2020 – 2026Roadway 87471000 · MP 33.3–39.4$7.6M
- SR 25/Okeechobee Rd From W Of Heft To W Of NW 138 StMiami-Dade County · 2020 – 2026Roadway 87471000 · MP 33.3–39.4$15.6M
- SR 25/Okeechobee Rd From W. Of NW 138 St To E. Of NW 107 Ave (Cncrete)Miami-Dade County · 2020 – 2026Roadway 87471000 · MP 33.3–39.4$37.7M
- SR 924 Gratigny West Extension To Heft (SR 821)Miami-Dade County · 2020 – 2026Roadway 87471000 · MP 33.3–39.4$4M
Opportunity Signals
- 14
- contracts up for bid
- $158.9M
- value at stake
- 2028-07
- next expiry
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$158.9M of work bids here by 2028 — be first to know the moment each RFQ drops.
Email notifications Activity dashboard Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Programmed in the FDOT Five-Year Work Program (FY 2026), managed by Florida's Turnpike Enterprise. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program
Project Timeline
PlanningComplete DesignComplete- ProcurementIn Progress
- ConstructionUpcomingOct 27, 2026
- CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
- CountyBroward County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
TPK Ext (SR821) Thru Lane Implementation (MP40.2-47)
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Aug 25, 2026- Estimated completion46 days
Remaining against FDOT's estimated contract completion date.
- Data freshness17 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
- Contract total (covers 2 projects)Σ FDOT Active Construction lines · contract E8W59
- $3.9M
- Construction cost (this project)Σ FDOT Active Construction lines for this project
- $712.1K
- Phase line item (44388245201)FDOT Active Construction
- $712.1K
Contract
FDOT record- Contract
- E8W59
- Prime contractor
- Ohla USA Inc
- FDOT project manager
- Pacifico Castillo
- Contract status
- Active
- Contract time (bid)
- 296 days
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
Project Activity
- Project milestone: Estimated completionUpcomingOct 27, 2026FDOT Construction Contracts
- Data sync: FDOT Active Construction re-readAug 25, 2026Scheduled data sync — no project fact necessarily changed
- Data sync: FDOT Work Program re-readAug 25, 2026Scheduled data sync — no project fact necessarily changed
- Data sync: FDOT Construction Contracts re-readAug 18, 2026Scheduled data sync — no project fact necessarily changed
- Project milestone: Notice to proceedJan 5, 2026FDOT Construction Contracts
- Project milestone: ExecutedDec 3, 2025FDOT Construction Contracts
- Project milestone: LetOct 21, 2025FDOT Construction Contracts
- Project milestone: Projected lettingOct 21, 2025FDOT Construction Contracts
Related Projects
Same Work Program item
Same roadway
- Heft Widening NW106TH To I75-DIVERGING Diamond Interchange NW 170Th StMiami-Dade County · 2020 – 2026Roadway 87471000 · MP 33.3–39.4$9.9M
- NB SR821 To NW107THAVE Buttonhook & NW107THAVE To NB SR821 FlyoverMiami-Dade County · 2020 – 2026Roadway 87471000 · MP 33.3–39.4$7.6M
- SR 25/Okeechobee Rd From W Of Heft To W Of NW 138 StMiami-Dade County · 2020 – 2026Roadway 87471000 · MP 33.3–39.4$15.6M
- SR 25/Okeechobee Rd From W. Of NW 138 St To E. Of NW 107 Ave (Cncrete)Miami-Dade County · 2020 – 2026Roadway 87471000 · MP 33.3–39.4$37.7M
- SR 924 Gratigny West Extension To Heft (SR 821)Miami-Dade County · 2020 – 2026Roadway 87471000 · MP 33.3–39.4$4M
Dates & milestones
- Contract completion (estimated)
- Oct 27, 2026
- Program year
- FY 2026
Identifiers
- FPID
- 443882-4-52-01
- Contract number
- E8W59
- Work Program item
- 443882
- District
- Turnpike
- County
- Broward
- Work mix (FDOT)
- Miscellaneous Constr
- FDOT status name
- CONTRACT EXECUTED
Sources & Data Confidence
View source details (19 facts)Hide source details
Not available for this project: district project page, federal funding.
| Fact | Value | Source | As of |
|---|---|---|---|
| Project name | TPK Ext (SR821) Thru Lane Implementation (MP40.2-47) | FDOT Work Program | Aug 25, 2026 |
| Status | Open for Pursuit | Derived from FDOT Work Program status (CONTRACT EXECUTED) | Aug 25, 2026 |
| FDOT status | CONTRACT EXECUTED | FDOT Work Program | Aug 25, 2026 |
| FPID | 443882-4-52-01 | FDOT Work Program | Aug 25, 2026 |
| Work Program item | 443882 | FDOT Work Program | Aug 25, 2026 |
| County | Broward | FDOT Work Program | Aug 25, 2026 |
| Limits | TPK Ext (SR821) Thru Lane Implementation (MP40.2-47) | FDOT Work Program | Aug 25, 2026 |
| Scope of work | Roadway Improvements | Derived from FDOT Work Program work mix (Miscellaneous Constr) | Aug 25, 2026 |
| Program year | FY 2026 | FDOT Work Program | Aug 25, 2026 |
| Contract total (covers 2 projects) | $3.9M | Σ FDOT Active Construction lines · contract E8W59 | Aug 25, 2026 |
| Construction cost (this project) | $712,100 | Σ FDOT Active Construction lines for this project | Aug 25, 2026 |
| Phase line item (44388245201) | $712,100 | FDOT Active Construction | Aug 25, 2026 |
| Contract completion (estimated) | 2026-10-27 | FDOT Active Construction | Aug 25, 2026 |
| Contract number | E8W59 | FDOT Construction Contracts | Aug 18, 2026 |
| Contract let | 2025-10-21 | FDOT Construction Contracts | Aug 18, 2026 |
| Notice to proceed | 2026-01-05 | FDOT Construction Contracts | Aug 18, 2026 |
| Prime contractor | Ohla USA Inc | FDOT Active Construction | Aug 25, 2026 |
| FDOT project manager | Pacifico Castillo | FDOT Active Construction | Aug 25, 2026 |
| Route geometry | Mapped route | FDOT Active Construction | Aug 25, 2026 |
Every fact in this record links to its published source. Where two sources disagree, both are shown rather than averaged or picked.
Lane closures & detours
Loading closure information…
Source: FDOT Work Zone Data Exchange. Publication is voluntary and may be incomplete.
14
Upcoming Bids
Confirmed · nearing bid
12
Upcoming Opportunities
CAP-backed · in Turnpike
$158.9M
Total Opportunity Value
Potential by 2028
Jul 2028
Next Bid
Soonest incumbent expiry
2028
Forecast Horizon
Through 2028
Opportunity Signals
Upcoming BidsConfirmed · incumbent contracts nearing bid14 Upcoming OpportunitiesCAP-backed · within Turnpike12
Bid counts are sourced. Upcoming Opportunities are CAP-backed and district-level.
Never miss what happens next.
Monitor this project and we’ll alert you the moment there’s movement—opportunities, awards, funding changes, team updates, and key milestones.
14
Future opportunities
identified
$158.9M
Potential value
by 2028
Planning
CompleteAward
In ProgressConstruction
UpcomingOperations
FutureOpportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Monitor This Project
Your intelligence team, on call.
Real-time alerts
Instant notifications when important updates happen
Activity dashboard
See all project activity in one central place
Weekly intelligence digest
Curated summary of what matters most
Unlimited project tracking
Follow all the projects you care about