SR 821 & Surface Street Improvements From Hainlin Mill To US 1(MP7-13)
Under Construction Turnpike Miami-Dade County, FL SR 821Resurfacing
Last updated Oct 15, 2026
Project summary
Roadway Improvements on SR 821 in Miami-Dade County.
Halley Engineering Contractors, Inc. has been building it for Florida's Turnpike Enterprise since Oct 8, 2025. FDOT estimates the contract finishes on Oct 14, 2027.
Construction contract value
$37.7M
Contract E8V40, this project only
Prime contractor
Halley Engineering Contractors, Inc.
FDOT record
Oct 8, 202556% of contract time elapsed · 325 days from todayOct 14, 2027
Counts and totals only. Incumbents, contract rows and bid timing are Pro.
Don’t get scooped on this work.
$156.7M of work bids here by 2028 — be first to know the moment each RFQ drops.
Email notifications
Activity dashboard
Cancel anytime
Opportunity announcements
New RFQs, RFPs, Solicitations
Contract awards
Winners, Award values, Award dates
Team & consultant changes
New firms, Teaming updates, Incumbent changes
Milestone & funding updates
Funding changes, Key milestones
Related corridor activity
New corridor projects
Unlock with TransitAtlas Pro to get full project intelligence and alerts.
Programmed in the FDOT Five-Year Work Program (FY 2025), managed by Florida's Turnpike Enterprise. Detailed fact sheets and outreach materials are published once construction approaches. View in the FDOT Work Program
Project Timeline
PlanningComplete
DesignComplete
ProcurementComplete
ConstructionIn ProgressOct 8, 2025 – Oct 14, 2027
CloseoutUpcoming
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 0.8 miN0.5 mi
RoadwaySR 821
CountyMiami-Dade County
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
SR 821 & Surface Street Improvements From Hainlin Mill To US 1(MP7-13)
Roadway Improvements
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed56%
Of the 24 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion325 days
Remaining against FDOT's estimated contract completion date.
Data freshness38 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Construction contract valueΣ FDOT Active Construction lines · contract E8V40
$37.7M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$37.7M
Phase line item (43721115201)FDOT Active Construction
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗