State Road (S.R.) A1A/South Ocean Boulevard Improvements Project from North of Emerald Beach Way to South of S.R. 704/ Royal Palm Way
Under Construction FDOT D4 Palm Beach County, FL SR A1ARoadway Improvements
Last updated Oct 15, 2026
Project summary
Resurfacing on S.R. A1A in Palm Beach County (2.3 miles).
S.R. A1A/South Ocean Boulevard from North of Emerald Beach Way to South of S.R. 704/ Royal Palm Way in the Town of Palm Beach
Halley Engineering Contractors, Inc. has been building it for FDOT District Four since May 27, 2025. FDOT's estimated contract completion was Sep 18, 2026.
Construction contract value
$8.7M
Contract E4W84, this project only
Prime contractor
Halley Engineering Contractors, Inc.
FDOT record
May 27, 2025100% of contract time elapsed · 64 days past the estimateSep 18, 2026
Phase order reflects standard FDOT delivery; only construction dates are sourced.
Project Location
≈ 2.3 miN0.5 mi
RoadwaySR A1A
CountyPalm Beach County
Length2.3 miles
Approximate route from FDOT Active Construction. Extent is indicative, not a survey.
Project Brief
S.R. A1A/South Ocean Boulevard from North of Emerald Beach Way to South of S.R. 704/ Royal Palm Way in the Town of Palm Beach
2.3 miles
Project length
Resurfacing
Scope of work
Project limits as published by FDOT. Scope categories are mapped from FDOT’s work-mix code list.
Project Health
as of Oct 15, 2026
Contract time elapsed100%
Of the 16 months between construction start and estimated contract completion. Time elapsed, not work completed — FDOT publishes no percent-complete figure.
Estimated completion64 days past
Today is past FDOT's estimated contract completion date. Contract time is routinely extended; this is the published estimate, not a finding of delay.
Cost sourcesDiffer by 5.5%
Measured between the district’s published project cost and the FDOT feed figure. Below the threshold used to flag a conflict — shown so the gap is visible rather than inferred from the absence of a warning.
Data freshness37 days ago
Last read from the FDOT feeds behind this record. Facts change when FDOT publishes, not when we sync.
Cost & funding
Construction contract valueΣ FDOT Active Construction lines · contract E4W84
$8.7M
Construction cost (this project)Σ FDOT Active Construction lines for this project
$8.7M
Project costFDOT district project site
$8.2M
Phase line item (44617515201)FDOT Active Construction
$7.7M
$3.8M / mileConstruction contract value ÷ 2.3 miles
Contract line items
446175-1-52-01This phase$7.7M
446175-1-52-02$867.8K
446175-1-52-03$65.3K
Each line is one FDOT financial-project sequence. The project total is their sum; a contract may additionally cover other projects, in which case its total is shown above as contract context rather than as this project's cost.
This project's financial-project sequences totalled from FDOT's construction contracts layer — an independent second reading of the cost shown under Cost & funding. The two services are derived separately, so agreement is corroboration rather than a restatement.
Contract facts · FDOT All Construction Contracts · synced Aug 18, 2026 · view source ↗
SWState Road (S.R.) A1A/South Ocean Boulevard Improvements Project from North of Emerald Beach Way to South of S.R. 704/ Royal Palm WayProject · centered
696th Avenue South Improvements at State Road (S.R.) 9/I-95Project
CRCounty Road (C.R.) 712/Midway Road Widening Project from west of Jenkins Road to Selvitz RoadProject
SBState Road (S.R.) 714/SW Martin Highway from east of SW Stuart W Boulevard to west of Citrus BoulevardProject
SAState Road (S.R.) A1A from Flamingo Avenue to South of Pine AveProject
SRState Road (S.R.) A1A from NE Shore Village Terrace to S.R. 732/Jensen Beach Causeway (RRR)Project